Detector Integration Schedule
schedule
updated on
Dec.26, 2003
by
H.Okuno
Dec.1 (Mon) Restart of the installation work by
Hutaba
Dec.2 (Tue)
#2
Dec.3 (Wed) #3
Dec.4 (Thu)
#4, #5
Dec.5 (Fri)
#6, #7, #8
Dec.6 (Sat)
Dec.7 (Sun)
Dec.8 (Mon)
#9, #10, #11
Dec.9 (Tue)
#12, #13, #14
Dec.10 (Wed)
#15, #16, #17
Dec.11 (Thu)
#18, #19,#20, #21
Dec.12 (Fri)
#22, #23, #24
Dec.13 (Sat)
#25, #26 ,#27
Dec.14 (Sun)
Dec.15 (Mon)
#28,#29, #30
Dec.16 (Tue)
#31, #32
Dec.17 (Wed)
Removal of the installation instruments
Dec.18 (Thu)
Charge Veto installation Attach FB vacuum cover
Dec.19 (Fri)
Charge Veto installation Attach FB vacuum cover
Dec.20 (Sat)
Charge Veto installation FB vacuum test
Dec.21 (Sun)
Dec.22 (Mon)
Reserve
Dec.23 (Tue)
Dec.24 (Wed)
Cooling pipe installation
Dec.25 (Thu) PMT
attachment
Dec.26 (Fri)
PMT attachment <--- current
status
Dec.27 (Sat)
Cable connection etc.
Dec.28
(Sun)
Dec.29 (Mon)
Dec.30 (Tue)
Dec.31 (Wed)
Jan.1(Thu)
Jan.2(Fri)
Jan.3(Sat)
Jan.4(Sun)
Jan.5(Mon)
Jan.6(Tue)
Jan.7(Wed)
Position measurement of the Downstream-section
Jan.8(Thu)
Remove the Upstream-section Cover(Hutaba)
Jan.9(Fri)
Positioning of the Middle section(Hutaba)
Position measurement of the Upstream-section
Installation of the Upstream membrane
Jan.10(Sat)
Jan.11(Sun)
Jan.12(Mon)
Jan.13(Tue)
Separation of the Upstream-section (Hutaba),
Replacement of the tir-tank (Hitachi-zosen)
Jan.14(Wed)
Jan.15(Thu)
Jan.16(Fri)
Jan.17(Sat)
Jan.18(Sun)
Jan.19(Mon)
Installation of the Downstream-section (Hutaba)
Jan.20(Tue)
Installation of the Downstream-section (Hutaba)
Jan.21(Wed)
Installation of the Upstream-section (Hutaba)
Jan.22(Thu)
Positioning of the Integrated Detector (Hutaba)
Jan.23(Fri)
Cable Rack installation (Hutaba)
Jan.24(Sat)
Jan.25(Sun)
Jan.26(Mon)
Installation of the Vacuum System
Jan.27(Tue)
Jan.28(Wed)
Jan.29(Thu)
Jan.30(Fri)
Jan.31(Sat)
Feb.1(Sun)
Feb.2(Mon)
Feb.3(Tue)
Feb.4(Wed)
Feb.5(Thu)
Feb.6(Fri)
Feb.7(Sat)
Feb.8(Sun)
Feb.9(Mon)
Feb.10(Tue)
Feb.11(Wed)
Feb.12(Thu)
Feb.13(Fri)
Feb.14 (Sat)
Feb.15(Sun)
Feb.16(Mon) BEAM
ON